skip to Main Content

Commissioning of Phase 1 Nearly Complete

The construction of IXcellerate's Phase One data hall is complete and commissioning is well underway.  Commissioning of the data centre incorporates testing all the equipment to ensure it is functioning properly.  The pictures below show heaters throughout the data centre…

Generators Arrive and Technical Equipment Installation Nearly Complete

IXcellerate's Phase One construction continues to progress on schedule.  Our Schneider-Anord power switchgear has been delivered and installed. It had dual A+B power feeds direct to our brand new transformers.  The two Emerson UPS systems have also been installed and…

Construction Progresses on Schedule with Floor Tile Installation

The construction of Phase One of IXcellerate's Moscow One Data Centre continues to progress on schedule. The raised flooring has begun to be installed and is nearly complete in the data hall, where racks for colocation and private suites will…

IXcellerate to Exhibit at Capacity Russia & CIS

IXcellerate will be an Exhibitor at Capacity Russia & CIS. buy and download photoshop elements 9 When: October 8th and 9th Where: Radisson SAS Slavyanskaya Hotel Europe Square, 2 - 121059 Moscow, Russia If you'd like to meet with IXcellerate, please Contact…

Power Cable Trenches Installation Begins

Phase 1 construction of IXcellerate's Moscow One Data Centre continues to progress with installation of power cables.  Last week, Mercury Engineering dug trenches from the building which houses our two transformer units.  We will be installing four cables for each…

Phase 1 Construction Continues: Walls and Ceiling Installed

Phase 1 of IXcellerate's 6,200 square metre data centre is continuing on schedule.  The construction team has spent the past week installing insulated sandwich panels, which comprise the walls and ceiling. They have also installed steel conduit tracks which will…

+7-495-8000-911
Back To Top